| Chapter | Hours-To-Date | Status | Left to finish | |
| 4 | Bulkheads | 23 | Complete | |
| 5 | Fuselage Sides | 27 | Complete | |
| 6 | Fuselage Assembly | 41 | Complete | |
| 7 | Fuselage Exterior | 18 | Complete | |
| 8 | Headrests and Seatbelts | 9 | In Process | Headrests, attach brkts |
| 9 | Landing Gear and Landing Brake | 51 | complete | |
| 10 | Canard | 34 | Complete | |
| 11 | Elevators | 14 | Complete | |
| 12 | Canard Installation | 11 | Started | |
| 13 | Nose Section | 40 | complete | |
| 14 | Center Spar | 55 | Complete | |
| 15 | Firewall | 0 | Not Started | |
| 16 | Control Systems | 0 | Not Started | |
| 17 | Trim Systems | 0 | Not Started | |
| 18 | Turtleback and Canopy | 36 | Started | |
| 19 | Wings | 124 | Complete | |
| 20 | Winglets and Rudders | 19 | In Process | cutout rudders |
| 21 | Strakes and Fuel Tanks | 14 | In Process | |
| 22 | Electrical Systems | 0 | Not Started | |
| 23 | Engine Installation | 4 | Not Started | |
| 24 | Covers and Fairings | 0 | Not Started | |
| 25 | Finishing | 0 | Not Started | |
| 26 | Upholstery | 0 | Not Started | |
| Total Hours | 520 | |||